Dept. of Trans. PROGRESS Serial No. Contract No. 09-358-10-22 08-007174 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 86% 71% 08-SBD-215-4.8/6.5 Federal Project: PNRS-6208(13) CML-6208(13) Progress payment No. 26 Payment period ending: 12-18-09 M C M CONSTRUCTION INC P O BOX 620 NORTH HIGHLANDS CA 95660 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 62,295,865.97 1,736,506.84 2.a. Extra Work 1,268,730.33 1,458.47 b. Adjustment Comp. 311,190.08 -121,994.60 3. Materials on Hand 712,294.40 16,506.51 4. Earned Subject to Retention 64,588,080.78 1,632,477.22 5. Mobilization 7,999,933.00 0.00 6. Total Work Completed 71,875,719.38 7. Deductions -5,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 72,583,013.78 1,632,477.22 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,632,477.22