Dept. of Trans. PROGRESS Serial No. Contract No. 10-113-14-16 08-007174 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 92% 88% 08-SBD-215-4.8/6.5 Federal Project: PNRS-6208(13) CML-6208(13) Progress payment No. 30 Payment period ending: 04-20-10 M C M CONSTRUCTION INC P O BOX 620 NORTH HIGHLANDS CA 95660 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 68,164,936.08 960,573.61 2.a. Extra Work 1,358,113.45 71,451.63 b. Adjustment Comp. 327,190.35 4,114.45 3. Materials on Hand 36,051.48 -33,086.91 4. Earned Subject to Retention 69,886,291.36 1,003,052.78 5. Mobilization 7,999,933.00 0.00 6. Total Work Completed 77,850,172.88 7. Deductions -25,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 77,861,224.36 1,003,052.78 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,003,052.78