Dept. of Trans. PROGRESS Serial No. Contract No. 10-299-16-16 08-007174 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 08-SBD-215-4.8/6.5 Federal Project: PNRS-6208(13) CML-6208(13) Progress payment No. 36 Payment period ending: 10-20-10 M C M CONSTRUCTION INC P O BOX 620 NORTH HIGHLANDS CA 95660 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 72,901,637.27 87,484.24 2.a. Extra Work 1,926,793.80 85,735.63 b. Adjustment Comp. 342,727.95 -85,521.94 3. Materials on Hand 4. Earned Subject to Retention 75,171,159.02 87,697.93 5. Mobilization 7,999,933.00 0.00 6. Total Work Completed 83,171,092.02 7. Deductions -34,170.37 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 83,136,921.65 87,697.93 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 87,697.93