Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 11-062-14-20 08-0A5504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 08-RIV-91-R0.1/5.9 Federal Project: 08-RIV-91-6.9/9.0 IM Progress payment No. 09 Payment period ending: 02-10-11 ALL AMERICAN ASPHALT P O BOX 2229 CORONA CA 928782229 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,827,235.53 97,655.09 2.a. Extra Work 132,458.38 14,231.32 b. Adjustment Comp. -116,198.49 0.00 3. Materials on Hand 4. Earned Subject to Retention 5,843,495.42 111,886.41 5. Mobilization 77,600.00 0.00 6. Total Work Completed 5,921,095.42 7. Deductions -10,000.00 -10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 5,911,095.42 101,886.41 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 101,886.41