Dept. of Trans. PROGRESS Serial No. Contract No. 11-299-08-58 08-0A6414 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 42% 55% 08-SBD-15-160.9/161.5 Federal Project: SARR-015-3(44) AE-015-3(44) STPE-015-3(44) Progress payment No. 05 Payment period ending: 10-20-11 RSB GROUP INC 22622 LAMBERT STREET NO 304 LAKE FOREST CA 92630 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 225,175.00 108,300.00 2.a. Extra Work 29,536.00 29,536.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 254,711.00 137,836.00 5. Mobilization 77,900.00 16,400.00 6. Total Work Completed 332,611.00 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 332,611.00 154,236.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 154,236.00