Dept. of Trans. PROGRESS Serial No. Contract No. 11-356-10-11 08-0C0204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 08-SBD-2-0.9/2.4 Federal Project: ACHS-P002(36) STPH-P002(36) Progress payment No. 08 Payment period ending: 12-19-11 PETERSON CHASE GENERAL ENGINEERING CONSTRUCTION INC 1792 KAISER AVENUE IRVINE CA 92614 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,266,314.13 912.00 2.a. Extra Work 90,826.25 0.00 b. Adjustment Comp. 48,824.31 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,405,964.69 912.00 5. Mobilization 49,000.00 0.00 6. Total Work Completed 1,454,964.69 7. Deductions -84,143.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,370,821.69 912.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 912.00