Dept. of Trans. PROGRESS Serial No. Contract No. 06-266-06-40 08-0C1804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 15% 17% 08-SBD-215-2.7/5.0 Federal Project: NONE Progress payment No. 03 Payment period ending: 09-20-06 BEADOR CONSTRUCTION COMPANY INC 26320 LESTER CIRCLE CORONA CA 92883 Escrow No. 02239 Total Estimate This Estimate 1. Contract Itms Without Mobil. 445,783.55 7,900.00 2.a. Extra Work 17,782.06 17,782.06 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 463,565.61 25,682.06 5. Mobilization 195,394.50 0.00 6. Total Work Completed 658,960.11 7. Deductions 8. a.Contract Retentions -46,356.56 -2,568.20 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 612,603.55 23,113.86 10. Reduction Amt to Escrow 11. Payment to Escrow 46,350.00 12. Net Pymt. this Estimate 23,113.86