Dept. of Trans. PROGRESS Serial No. Contract No. 08-298-11-07 08-0C3304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 56% 78% 08-SBD-10-0.0/R39.1 Federal Project: NONE Progress payment No. 02 Payment period ending: 10-20-08 HIGHLAND CONSTRUCTION INC 133 NORTH PIXLEY STREET ORANGE CA 92868 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 406,374.30 190,483.20 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 406,374.30 190,483.20 5. Mobilization 6. Total Work Completed 406,374.30 7. Deductions 8. a.Contract Retentions -20,318.72 -6,349.12 b. Unsatisfactory Prog. -9,524.16 -9,524.16 c. Reduction after 95% Comp. 9. Total pay to Contractor 376,531.42 174,609.92 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 174,609.92