Dept. of Trans. PROGRESS Serial No. Contract No. 09-114-12-59 08-0C3314 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 11% 24% 08-SBD-10-0.0/39.2 Federal Project: NONE Progress payment No. 01 Payment period ending: 04-20-09 POWELL CONSTRUCTORS 8555 BANANA AVENUE FONTANA CA 92335 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 77,821.00 77,821.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 77,821.00 77,821.00 5. Mobilization 6. Total Work Completed 77,821.00 7. Deductions 8. a.Contract Retentions -7,782.10 -7,782.10 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 70,038.90 70,038.90 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 70,038.90