Dept. of Trans. PROGRESS Serial No. Contract No. 09-296-14-04 08-0C5104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 08-SBD-40-R142.2/R142.6 Federal Project: NONE Progress payment No. 19 Payment period ending: 10-20-09 DIVERSIFIED LANDSCAPE MANAGEMENT INC 23052-H ALICIA PARKWAY, #385 MISSION VIEJO, CA 92692 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 336,894.41 1,558.50 2.a. Extra Work 17,952.67 0.00 b. Adjustment Comp. 6,895.20 0.00 3. Materials on Hand 4. Earned Subject to Retention 361,742.28 1,558.50 5. Mobilization 54,000.00 0.00 6. Total Work Completed 415,742.28 7. Deductions -11,494.21 0.00 8. a.Contract Retentions -18,087.11 -77.92 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 386,160.96 1,480.58 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,480.58