Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 12-110-13-26 08-0C7424 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 08-SBD-210-0.0/33.2 Federal Project: ACNH-000C(338) Progress payment No. 03 Payment period ending: 03-19-12 MYERS AND SONS HI WAY SAFETY INC P O BOX 1030 CHINO CA 91708 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 327,910.69 124,388.06 2.a. Extra Work 22,425.72 22,425.72 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 350,336.41 146,813.78 5. Mobilization 6. Total Work Completed 350,336.41 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 350,336.41 146,813.78 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 146,813.78