Dept. of Trans. FINAL Serial No. Contract No. 06-158-08-07 08-0C9814 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 08-RIV-86-R18.1/R21.5 Federal Project: NONE Progress payment No. 08 Payment period ending: 02-17-06 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 95077 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,800,520.39 0.00 2.a. Extra Work 17,667.52 0.00 b. Adjustment Comp. -7,962.54 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,810,225.37 0.00 5. Mobilization 246,500.00 0.00 6. Total Work Completed 2,056,725.37 7. Deductions 8. a.Contract Retentions -89,825.69 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 89,825.69 0.00 9. Total pay to Contractor 2,056,725.37 0.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 0.00