Dept. of Trans. PROGRESS Serial No. Contract No. Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 05-235-08-53 05-0H1004 05-200-07-41 08-0E0604 PROGRESS PAYMENT VOUCHER %complete: %time: PROGRESS PAYMENT VOUCHER %complete: %time: Location: 96% 87% Location: 100% 100% 05-MON-101-69.4/73.9 Federal Project: 08-SBD-18-T6.0/R11.2 Federal Project: ACST-Q101(90) NONE PHG-Q101(90) Progress payment No. 06 Payment period ending: 08-20-05 PAVEX CONSTRUCTION DIVISION 330 BLOMQUIST STREET Progress payment No. 03 Payment period ending: 06-30-05 REDWOOD CITY CA 94063 ALL AMERICAN ASPHALT P O BOX 2229 Escrow No. 00000 CORONA CA 928782229 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,015,044.05 144,839.00 2.a. Extra Work 26,041.89 0.00 Escrow No. 00000 b. Adjustment Comp. Total Estimate This Estimate 1. Contract Itms Without Mobil. 895,556.94 143,837.99 3. Materials on Hand 2.a. Extra Work 71,845.00 14,418.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 2,041,085.94 144,839.00 4. Earned Subject to Retention 967,401.94 158,255.99 5. Mobilization 200,000.00 0.00 5. Mobilization 6. Total Work Completed 2,241,085.94 6. Total Work Completed 967,401.94 7. Deductions 7. Deductions -1,000.00 -1,000.00 8. a.Contract Retentions 8. a.Contract Retentions -40,457.30 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 2,241,085.94 144,839.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 144,839.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 40,457.30 40,457.30 9. Total pay to Contractor 966,401.94 197,713.29 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 197,713.29