Dept. of Trans. PROGRESS Serial No. Contract No. 23-205-20-27 08-0E33U4 PROGRESS PAYMENT VOUCHER %complete: %time: 43% 55% Location: Federal Project: 08-SBD-60-R7.3/R10.0 ACNH-P060(159) Progress payment No. 022 Payment period ending: 07-20-23 AMES CONSTRUCTION INC 2500 COUNTY RD 42 W BURNSVILLE MN 55337 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 8,181,278.05 756,067.95 2. a. Extra Work 497,863.56 25,996.91 b. Adustment Comp. 926,055.77 268,151.92 3. Materials on Hand 994,740.03 -13,225.70 4. Earned Subject to Retention 10,599,937.41 1,036,991.08 5. Mobilization 1,431,650.71 0.00 6. Total Work Completed 11,036,848.09 7. Deductions -31,920.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 11,999,668.12 1,036,991.08 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,036,991.08