Dept. of Trans. PROGRESS Serial No. Contract No. 23-356-16-17 08-0E33U4 PROGRESS PAYMENT VOUCHER %complete: %time: 87% 63% Location: Federal Project: 08-SBD-60-R7.3/R10.0 ACNH-P060(159) Progress payment No. 027 Payment period ending: 12-20-23 AMES CONSTRUCTION INC 2500 COUNTY RD 42 W BURNSVILLE MN 55337 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 19,994,178.25 1,370,241.79 2. a. Extra Work 837,498.36 74,039.03 b. Adustment Comp. 1,084,846.13 68,536.81 3. Materials on Hand 24.00 -141,531.79 4. Earned Subject to Retention 21,916,546.74 1,371,285.84 5. Mobilization 1,507,000.75 0.00 6. Total Work Completed 23,423,523.49 7. Deductions -644,480.90 62,440.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 22,779,066.59 1,433,725.84 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,433,725.84