Dept. of Trans. PROGRESS Serial No. Contract No. 24-113-12-35 08-0E33U4 PROGRESS PAYMENT VOUCHER %complete: %time: 95% 65% Location: Federal Project: 08-SBD-60-R7.3/R10.0 ACNH-P060(159) Progress payment No. 032 Payment period ending: 04-20-24 AMES CONSTRUCTION INC 2500 COUNTY RD 42 W BURNSVILLE MN 55337 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 22,074,628.65 545,273.35 2. a. Extra Work 936,112.95 -52,278.69 b. Adustment Comp. 1,185,274.63 0.00 3. Materials on Hand 4. Earned Subject to Retention 24,196,016.23 492,994.66 5. Mobilization 1,507,000.75 0.00 6. Total Work Completed 25,703,016.98 7. Deductions -679,920.90 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 25,023,096.08 492,994.66 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 492,994.66