Dept. of Trans. PROGRESS Serial No. Contract No. 24-165-16-23 08-0E33U4 PROGRESS PAYMENT VOUCHER %complete: %time: 96% 65% Location: Federal Project: 08-SBD-60-R7.3/R10.0 ACNH-P060(159) Progress payment No. 034 Payment period ending: 06-20-24 AMES CONSTRUCTION INC 2500 COUNTY RD 42 W BURNSVILLE MN 55337 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 22,455,436.45 129,678.50 2. a. Extra Work 1,080,762.39 170,520.43 b. Adustment Comp. 1,287,490.22 -209.89 3. Materials on Hand 4. Earned Subject to Retention 24,823,689.06 299,989.04 5. Mobilization 1,507,000.75 0.00 6. Total Work Completed 26,330,689.81 7. Deductions -712,488.87 21,662.45 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 25,618,200.94 321,651.49 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 321,651.49