Dept. of Trans. PROGRESS Serial No. Contract No. 25-080-16-48 08-0E33U4 PROGRESS PAYMENT VOUCHER %complete: %time: 97% 94% Location: Federal Project: 08-SBD-60-R7.3/R10.0 ACNH-P060(159) Progress payment No. 043 Payment period ending: 03-20-25 AMES CONSTRUCTION INC 2500 COUNTY RD 42 W BURNSVILLE MN 55337 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 22,789,076.10 7,200.00 2. a. Extra Work 1,350,373.94 -13,952.49 b. Adustment Comp. 1,294,054.05 3,686.23 3. Materials on Hand 4. Earned Subject to Retention 25,433,504.09 -3,066.26 5. Mobilization 1,507,000.75 0.00 6. Total Work Completed 26,940,504.84 7. Deductions -64,487.97 81,000.90 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 26,876,016.87 77,934.64 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 77,934.64