Dept. of Trans. PROGRESS Serial No. Contract No. 08-172-11-02 08-0E5804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 93% 100% 08-SBD-30-R31.1/R31.2 Federal Project: NONE Progress payment No. 04 Payment period ending: 06-12-08 RSB GROUP INC 22600 G LAMBERT ST NO 1405 LAKE FOREST CA 92630 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 349,562.50 135,638.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 349,562.50 135,638.00 5. Mobilization 42,600.00 0.00 6. Total Work Completed 392,162.50 7. Deductions -1,311.95 0.00 8. a.Contract Retentions -17,478.13 -6,781.90 b. Unsatisfactory Prog. -14,114.40 -6,781.90 c. Reduction after 95% Comp. 9. Total pay to Contractor 359,258.02 122,074.20 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 122,074.20