Dept. of Trans. SEMI-FINAL Serial No. Contract No. 12-075-08-38 08-0E8504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 08-SBD-58-T1.3/9.8 Federal Project: ACHS-P058(109) NJ-P058(109) Progress payment No. 11 Payment period ending: 08-19-11 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 950775085 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 11,155,920.34 -30,000.06 2.a. Extra Work 87,128.22 0.00 b. Adjustment Comp. 681,189.44 7,500.00 3. Materials on Hand 4. Earned Subject to Retention 11,924,238.00 -22,500.06 5. Mobilization 250,000.00 0.00 6. Total Work Completed 12,174,238.00 7. Deductions 0.00 63,166.95 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 12,174,238.00 40,666.89 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 40,666.89