Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 04-365-11-01 08-0E9604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 08-SBD-18-17.8/21.4 Federal Project: NH Progress payment No. 10 Payment period ending: 10-06-04 SEMA CONSTRUCTION INC 2 SOUTH POINTE DRIVE STE 295 LAKE FOREST CA 92630 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2.a. Extra Work 5,133,687.65 55,210.90 b. Adjustment Comp. -2,353.73 -2,353.73 3. Materials on Hand 4. Earned Subject to Retention 5,131,333.92 52,857.17 5. Mobilization 6. Total Work Completed 5,131,333.92 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 5,131,333.92 52,857.17 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 52,857.17