Dept. of Trans. PROGRESS Serial No. Contract No. 05-207-13-54 08-0E9704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 71% 86% 08-SBD-210-0.0/15.0 Federal Project: NONE Progress payment No. 04 Payment period ending: 07-20-05 STERNDAHL ENTERPRISES INC 11861 BRANFORD ST SUN VALLEY CA 91352 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 349,419.00 158,581.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 349,419.00 158,581.00 5. Mobilization 6. Total Work Completed 349,419.00 7. Deductions 8. a.Contract Retentions -17,470.95 -7,682.95 b. Unsatisfactory Prog. -7,929.05 -7,929.05 c. Reduction after 95% Comp. 9. Total pay to Contractor 324,019.00 142,969.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 142,969.00