Dept. of Trans. PROGRESS Serial No. Contract No. 21-113-10-53 08-0F0304 PROGRESS PAYMENT VOUCHER %complete: %time: 69% 54% Location: Federal Project: 08-SBD-60-0.7/3.0 B1NH-P060(153) Progress payment No. 024 Payment period ending: 04-20-21 SEMA CONSTRUCTION INC 42690 RIO NEDO #G TEMECULA CA 92590 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 10,758,779.58 440,910.10 2. a. Extra Work 835,803.50 17,978.68 b. Adustment Comp. 318.96 0.00 3. Materials on Hand 832,765.37 -38,544.50 4. Earned Subject to Retention 12,427,667.41 420,344.28 5. Mobilization 1,811,319.87 0.00 6. Total Work Completed 13,406,221.91 7. Deductions -420,697.46 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 13,818,289.82 420,344.28 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 420,344.28