Dept. of Trans. PROGRESS Serial No. Contract No. 11-237-14-16 08-0F1004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 64% 82% 08-SBD-71-4.8/8.5 Federal Project: 08-RIV-71-0.0/2.7 SARR-STPE(P07) AEST-PEP0(710) Progress payment No. 05 Payment period ending: 08-19-11 PACIFIC RESTORATION GROUP INC P O BOX 429 PERRIS CA 92572 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 210,526.50 131,164.80 2.a. Extra Work b. Adjustment Comp. 4,725.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 215,251.50 131,164.80 5. Mobilization 19,000.00 4,000.00 6. Total Work Completed 234,251.50 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. -13,116.48 -13,116.48 c. Reduction after 95% Comp. 9. Total pay to Contractor 221,135.02 122,048.32 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 122,048.32