Dept. of Trans. PROGRESS Serial No. Contract No. 06-114-15-03 08-0F2704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 6% 10% 08-SBD-10-R23.2/ .0 Federal Project: NONE Progress payment No. 01 Payment period ending: 04-20-06 BEADOR CONSTRUCTION COMPANY INC 26320 LESTER CIRCLE CORONA CA 92883 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 10,850.00 10,850.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 10,850.00 10,850.00 5. Mobilization 6. Total Work Completed 10,850.00 7. Deductions 8. a.Contract Retentions -1,085.00 -1,085.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 9,765.00 9,765.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 9,765.00