Dept. of Trans. SEMI-FINAL Serial No. Contract No. 05-326-07-28 08-0F4604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 08-RIV-79-9.0/15.0 Federal Project: NONE Progress payment No. 04 Payment period ending: 08-01-05 MANHOLE ADJUSTING CONTRACTORS INC 9500 BEVERLY ROAD PICO RIVERA CA 906602135 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 762,992.48 0.00 2.a. Extra Work 9,303.80 0.00 b. Adjustment Comp. 15,235.53 15,235.53 3. Materials on Hand 4. Earned Subject to Retention 787,531.81 15,235.53 5. Mobilization 6. Total Work Completed 787,531.81 7. Deductions -1,800.00 13,200.00 8. a.Contract Retentions -31,899.73 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 31,899.73 0.00 9. Total pay to Contractor 785,731.81 28,435.53 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 28,435.53