Dept. of Trans. FINAL Serial No. Contract No. 06-038-08-07 08-0F4904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 08-SBD-15-R16.0/30.0 Federal Project: NONE Progress payment No. 06 Payment period ending: 12-15-05 ALL AMERICAN ASPHALT P O BOX 2229 CORONA CA 92878 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 565,710.00 0.00 2.a. Extra Work 42,150.00 0.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 607,860.00 0.00 5. Mobilization 6. Total Work Completed 607,860.00 7. Deductions -24,208.00 0.00 8. a.Contract Retentions -27,077.15 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 27,077.15 0.00 9. Total pay to Contractor 583,652.00 0.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 0.00