Dept. of Trans. PROGRESS Serial No. Contract No. 14-328-15-21 08-0G2904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 2% 22% 08-SBD-15-12.8/ .0 Federal Project: IM-015-5(160) CITY Progress payment No. 01 Payment period ending: 11-18-14 ALL AMERICAN ASPHALT P.O. BOX 2229 CORONA, CA 928782229 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 52,481.54 52,481.54 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 52,481.54 52,481.54 5. Mobilization 6. Total Work Completed 52,481.54 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 52,481.54 52,481.54 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 52,481.54