Dept. of Trans. PROGRESS Serial No. Contract No. 15-057-07-14 08-0G2904 PROGRESS PAYMENT VOUCHER %complete: %time: 45% 70% Location: Federal Project: 08-SBD-15-12.8 IM-015-5(160) CITY- Progress payment No. 004 Payment period ending: 02-19-15 ALL AMERICAN ASPHALT P.O. BOX 2229 CORONA, CA 928782229 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 913,636.28 552,710.12 2. a. Extra Work 5,051.94 3,443.96 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 918,688.22 556,154.08 5. Mobilization 74,100.00 15,600.00 6. Total Work Completed 992,788.22 7. Deductions -7,000.00 -3,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 985,788.22 568,754.08 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 568,754.08