Dept. of Trans. PROGRESS Serial No. Contract No. 15-205-15-50 08-0G2904 PROGRESS PAYMENT VOUCHER %complete: %time: 92% 100% Location: Federal Project: 08-SBD-15-12.8 IM-015-5(160) CITY Progress payment No. 009 Payment period ending: 07-20-15 ALL AMERICAN ASPHALT P.O. BOX 2229 CORONA, CA 928782229 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,062,569.41 26,729.50 2. a. Extra Work 73,862.99 43,115.93 b. Adustment Comp. -134,823.58 0.00 3. Materials on Hand 4. Earned Subject to Retention 2,001,608.82 69,845.43 5. Mobilization 78,000.00 0.00 6. Total Work Completed 2,079,608.82 7. Deductions -4,000.00 -4,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,075,608.82 65,845.43 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 65,845.43