Dept. of Trans. PROGRESS Serial No. Contract No. 09-267-16-23 08-0G4104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 13% 57% 08-SBD-15-22.5/ .0 Federal Project: ACIM-4133(4) ACIM-4133 Progress payment No. 02 Payment period ending: 09-17-09 SLATER INC P O BOX 759 FONTANA CA 92334 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 80,409.50 40,570.50 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 80,409.50 40,570.50 5. Mobilization 6. Total Work Completed 80,409.50 7. Deductions -5,575.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 74,834.50 40,570.50 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 40,570.50