Dept. of Trans. PROGRESS Serial No. Contract No. 07-269-10-32 08-0G4604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 33% 100% 08-RIV-60-28.8/29.8 Federal Project: ACST-P060(133) PHG-P060(133) Progress payment No. 03 Payment period ending: 09-20-07 MODERN ALLOYS INC 11172 WESTERN AVENUE STANTON CA 90680 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 433,603.30 159,590.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 433,603.30 159,590.00 5. Mobilization 142,500.00 30,000.00 6. Total Work Completed 576,103.30 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. -15,959.00 -15,959.00 c. Reduction after 95% Comp. 9. Total pay to Contractor 560,144.30 173,631.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 173,631.00