Dept. of Trans. PROGRESS Serial No. Contract No. 12-116-15-28 08-0G4804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 59% 73% 08-SBD-15-R111.6/R124.2 Federal Project: IM-152(36) Progress payment No. 04 Payment period ending: 04-19-12 BUILDING CONSULTING ENGINEERS INC 14616 MCKENDREE AVENUE CHINO CA 91710 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 660,915.00 415,685.00 2.a. Extra Work 19,100.00 8,200.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 680,015.00 423,885.00 5. Mobilization 237,500.00 50,000.00 6. Total Work Completed 917,515.00 7. Deductions -96,661.64 -20,349.82 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 820,853.36 453,535.18 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 453,535.18