Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 24-325-10-14 08-0G6904 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 08-SBD-18-44.3/68.5 NONE Progress payment No. 010 Payment period ending: 11-04-24 BEADOR CONSTRUCTION COMPANY INC 26320 LESTER CIR CORONA CA 92883 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,897,275.00 31,900.00 2. a. Extra Work 35,040.32 15,165.08 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 2,932,315.32 47,065.08 5. Mobilization 356,406.00 0.00 6. Total Work Completed 3,288,721.32 7. Deductions 0.00 1,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 3,288,721.32 48,065.08 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 48,065.08