Dept. of Trans. PROGRESS Serial No. Contract No. 08-144-15-24 08-0G7004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 0% 18% 08-RIV-10-105.0/134.3 Federal Project: NONE Progress payment No. 01 Payment period ending: 05-20-08 FNF CONSTRUCTION INC 115 SOUTH 48TH STREET TEMPE AZ 85281 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 10,625.00 10,625.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 10,625.00 10,625.00 5. Mobilization 6. Total Work Completed 10,625.00 7. Deductions 8. a.Contract Retentions -1,062.50 -1,062.50 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 9,562.50 9,562.50 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 9,562.50