Dept. of Trans. PROGRESS Serial No. Contract No. 09-085-12-43 08-0H2824 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 39% 26% 08-SBD-5730 Federal Project: NONE Progress payment No. 11 Payment period ending: 03-20-09 DJM CONSTRUCTION CO INC 1540 S LEWIS ST ANAHEIM CA 92805 Escrow No. 02381 Total Estimate This Estimate 1. Contract Itms Without Mobil. 10,234,449.11 914,187.93 2.a. Extra Work 76,623.96 6,828.91 b. Adjustment Comp. 117,652.33 5,003.84 3. Materials on Hand 4. Earned Subject to Retention 10,428,725.40 926,020.68 5. Mobilization 6. Total Work Completed 10,428,725.40 7. Deductions -467,501.25 -46,712.50 8. a.Contract Retentions -536,190.56 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 9,425,033.59 879,308.18 10. Reduction Amt to Escrow 11. Payment to Escrow 536,190.00 12. Net Pymt. this Estimate 879,308.18