Dept. of Trans. PROGRESS Serial No. Contract No. 09-208-13-27 08-0H2824 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 50% 38% 08-SBD-5730 Federal Project: NONE Progress payment No. 15 Payment period ending: 07-20-09 DJM CONSTRUCTION CO INC 1540 S LEWIS ST ANAHEIM CA 92805 Escrow No. 02381 Total Estimate This Estimate 1. Contract Itms Without Mobil. 13,199,916.55 723,660.63 2.a. Extra Work 399,931.53 145,829.13 b. Adjustment Comp. 216,349.01 29,112.38 3. Materials on Hand 4. Earned Subject to Retention 13,816,197.09 898,602.14 5. Mobilization 6. Total Work Completed 13,816,197.09 7. Deductions -647,272.50 -48,106.25 8. a.Contract Retentions -690,809.85 -44,930.10 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 12,478,114.74 805,565.79 10. Reduction Amt to Escrow 11. Payment to Escrow 690,800.00 12. Net Pymt. this Estimate 805,565.79