Dept. of Trans. PROGRESS Serial No. Contract No. 10-113-14-07 08-0H2824 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 87% 63% 08-SBD-5730 Federal Project: NONE Progress payment No. 25 Payment period ending: 04-20-10 DJM CONSTRUCTION CO INC 1540 S LEWIS ST ANAHEIM CA 92805 Escrow No. 02381 Total Estimate This Estimate 1. Contract Itms Without Mobil. 23,115,793.88 611,479.66 2.a. Extra Work 982,174.00 200,117.00 b. Adjustment Comp. 393,626.09 22,897.00 3. Materials on Hand 201,991.16 0.00 4. Earned Subject to Retention 24,693,585.13 834,493.66 5. Mobilization 6. Total Work Completed 24,491,593.97 7. Deductions -1,095,333.75 -47,686.25 8. a.Contract Retentions -1,234,679.26 -41,724.69 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 22,363,572.12 745,082.72 10. Reduction Amt to Escrow 11. Payment to Escrow 1,234,670.00 12. Net Pymt. this Estimate 745,082.72