Dept. of Trans. PROGRESS Serial No. Contract No. 10-266-12-51 08-0H2824 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 94% 79% 08-SBD-5730 Federal Project: NONE Progress payment No. 30 Payment period ending: 09-16-10 DJM CONSTRUCTION CO INC 1540 S LEWIS ST ANAHEIM CA 92805 Escrow No. 02381 Total Estimate This Estimate 1. Contract Itms Without Mobil. 25,393,029.40 164,301.89 2.a. Extra Work 1,315,409.45 45,573.74 b. Adjustment Comp. 466,813.12 -2,572.17 3. Materials on Hand 4. Earned Subject to Retention 27,175,251.97 207,303.46 5. Mobilization 6. Total Work Completed 27,175,251.97 7. Deductions -1,335,445.00 -38,483.75 8. a.Contract Retentions -1,358,762.60 -10,365.17 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 24,481,044.37 158,454.54 10. Reduction Amt to Escrow 11. Payment to Escrow 1,358,760.00 12. Net Pymt. this Estimate 158,454.54