Dept. of Trans. PROGRESS Serial No. Contract No. 20-114-13-10 08-0H4704 PROGRESS PAYMENT VOUCHER %complete: %time: 80% 85% Location: Federal Project: 08-SBD-2-2.4 B1ST-P002-0(40) Progress payment No. 012 Payment period ending: 04-20-20 BEADOR CONSTRUCTION COMPANY 26320 LESTER CIR CORONA CA 92883 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,188,056.88 482,072.25 2. a. Extra Work 82,823.23 6,900.00 b. Adustment Comp. 40,057.10 0.00 3. Materials on Hand 25,319.88 14,851.00 4. Earned Subject to Retention 2,336,257.09 503,823.25 5. Mobilization 164,650.00 0.00 6. Total Work Completed 2,475,587.21 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,500,907.09 503,823.25 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 503,823.25