Dept. of Trans. PROGRESS Serial No. Contract No. 06-145-15-28 08-0H5804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 21% 20% 08-SBD-138-29.1/37.8 Federal Project: 08-SBD-189-0.0/5.6 NH 08-SBD-173-10.8/23.1 Progress payment No. 02 Payment period ending: 05-20-06 SOUTH BAY TIMBER 202 N. OREGON ST. YREKA, CA 96067 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2.a. Extra Work 424,136.17 374,136.17 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 424,136.17 374,136.17 5. Mobilization 6. Total Work Completed 424,136.17 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 424,136.17 374,136.17 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 374,136.17