Dept. of Trans. PROGRESS Serial No. Contract No. 08-239-11-24 08-0H8414 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 08-SBD-83-10.6/ .0 Federal Project: NONE Progress payment No. 02 Payment period ending: 08-20-08 BELAIRE WEST LANDSCAPE INC P O BOX 6270 BUENA PARK CA 90622 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 75,020.00 44,867.50 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 75,020.00 44,867.50 5. Mobilization 6. Total Work Completed 75,020.00 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 75,020.00 44,867.50 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 44,867.50