Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 09-162-10-01 08-0H9904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 08-RIV-10-R52.3/R57.0 Federal Project: ACHS-104(59) IMG-104(59) Progress payment No. 04 Payment period ending: 05-28-09 D C HUBBS CONSTRUCTION 37306 VISTA VIEW DRIVE YUCAIPA CA 92399 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 930,689.65 149,327.75 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 930,689.65 149,327.75 5. Mobilization 30,300.00 0.00 6. Total Work Completed 960,989.65 7. Deductions -10,000.00 -10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 950,989.65 139,327.75 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 139,327.75