Dept. of Trans. PROGRESS Serial No. Contract No. 14-148-15-45 08-0J0104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 14% 31% 08-SBD-18-53.4/53.6 Federal Project: HSNH-P018(44) Progress payment No. 01 Payment period ending: 05-21-14 DREAMBUILDER CONSTRUCTION CORP DBA DREAMBUILDER 1324 E LAWSON LN PLACENTIA CA 92870 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 69,320.97 69,320.97 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 69,320.97 69,320.97 5. Mobilization 6. Total Work Completed 69,320.97 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 69,320.97 69,320.97 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 69,320.97