Dept. of Trans. PROGRESS Serial No. Contract No. 18-116-08-34 08-0J0704 PROGRESS PAYMENT VOUCHER %complete: %time: 15% 11% Location: Federal Project: 08-SBD-215-0.0/2.7 04LN-6208(23) 08-RIV-215-45.1/45.3 Progress payment No. 004 Payment period ending: 04-20-18 MYERS-RADOS A JOINT VENTURE 4600 NORTHGATE BLVD #100 SACRAMENTO CA 95834 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,774,579.59 1,880,997.13 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 991,976.24 -55,625.93 4. Earned Subject to Retention 5,766,555.83 1,825,371.20 5. Mobilization 2,583,450.81 861,150.27 6. Total Work Completed 7,358,030.40 7. Deductions -3,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 8,347,006.64 2,686,521.47 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,686,521.47