Dept. of Trans. PROGRESS Serial No. Contract No. 19-022-11-55 08-0J0704 PROGRESS PAYMENT VOUCHER %complete: %time: 51% 42% Location: Federal Project: 08-SBD-215-0.0/2.7 04LN-6208(23) 08-RIV-215-45.1/45.3 Progress payment No. 013 Payment period ending: 01-20-19 MYERS-RADOS A JOINT VENTURE 4600 NORTHGATE BLVD #100 SACRAMENTO CA 95834 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 21,470,650.08 1,074,600.44 2. a. Extra Work 171,481.35 0.00 b. Adustment Comp. 23,781.15 0.00 3. Materials on Hand 303,019.91 -10,499.50 4. Earned Subject to Retention 21,968,932.49 1,064,100.94 5. Mobilization 3,272,371.03 0.00 6. Total Work Completed 24,938,283.61 7. Deductions -35,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 25,206,303.52 1,064,100.94 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,064,100.94