Dept. of Trans. PROGRESS Serial No. Contract No. 19-056-10-08 08-0J0704 PROGRESS PAYMENT VOUCHER %complete: %time: 56% 45% Location: Federal Project: 08-SBD-215-0.0/2.7 04LN-6208(23) 08-RIV-215-45.1/45.3 Progress payment No. 014 Payment period ending: 02-20-19 MYERS-RADOS A JOINT VENTURE 4600 NORTHGATE BLVD #100 SACRAMENTO CA 95834 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 23,127,452.16 1,656,802.05 2. a. Extra Work 254,321.72 82,840.37 b. Adustment Comp. 80,229.50 56,448.35 3. Materials on Hand 300,808.91 -2,211.00 4. Earned Subject to Retention 23,762,812.29 1,793,879.77 5. Mobilization 3,444,601.08 172,230.05 6. Total Work Completed 26,906,604.46 7. Deductions -45,000.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 27,162,413.37 1,956,109.82 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,956,109.82