Dept. of Trans. PROGRESS Serial No. Contract No. 19-169-10-23 08-0J0704 PROGRESS PAYMENT VOUCHER %complete: %time: 67% 59% Location: Federal Project: 08-SBD-215-0.0/2.7 04LN-6208(23) 08-RIV-215-45.1/45.3 Progress payment No. 018 Payment period ending: 06-20-19 MYERS-RADOS A JOINT VENTURE 4600 NORTHGATE BLVD #100 SACRAMENTO CA 95834 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 28,466,826.78 1,362,538.44 2. a. Extra Work 486,551.27 29,242.84 b. Adustment Comp. 89,516.67 0.00 3. Materials on Hand 300,497.41 142,824.35 4. Earned Subject to Retention 29,343,392.13 1,534,605.63 5. Mobilization 3,444,601.08 0.00 6. Total Work Completed 32,487,495.80 7. Deductions -45,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 32,742,993.21 1,534,605.63 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,534,605.63