Dept. of Trans. PROGRESS Serial No. Contract No. 20-084-12-22 08-0J0704 PROGRESS PAYMENT VOUCHER %complete: %time: 90% 89% Location: Federal Project: 08-SBD-215-0.0/2.7 04LN-6208(23) 08-RIV-215-45.1/45.3 Progress payment No. 027 Payment period ending: 03-20-20 MYERS-RADOS A JOINT VENTURE 4600 NORTHGATE BLVD #100 SACRAMENTO CA 95834 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 39,366,551.26 1,108,950.75 2. a. Extra Work 796,060.46 35,455.43 b. Adustment Comp. 74,733.57 -91,334.80 3. Materials on Hand 4,356.60 -14,965.23 4. Earned Subject to Retention 40,241,701.89 1,038,106.15 5. Mobilization 3,444,601.08 0.00 6. Total Work Completed 43,681,946.37 7. Deductions -50,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 43,636,302.97 1,038,106.15 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,038,106.15