Dept. of Trans. PROGRESS Serial No. Contract No. 20-234-09-49 08-0J0704 PROGRESS PAYMENT VOUCHER %complete: %time: 97% 99% Location: Federal Project: 08-SBD-215-0.0/2.7 04LN-6208(23) 08-RIV-215-45.1/45.3 Progress payment No. 032 Payment period ending: 08-20-20 MYERS-RADOS A JOINT VENTURE 4600 NORTHGATE BLVD #100 SACRAMENTO CA 95834 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 43,367,645.00 154,936.04 2. a. Extra Work 1,158,180.13 81,659.43 b. Adustment Comp. -18,450.44 0.00 3. Materials on Hand 4. Earned Subject to Retention 44,507,374.69 236,595.47 5. Mobilization 3,444,601.08 0.00 6. Total Work Completed 47,951,975.77 7. Deductions -50,000.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 47,901,975.77 226,595.47 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 226,595.47